Standards for punctures in the road surface when laying a water pipe

Alexei
1
answer
185
views

Good afternoon. When trenchless laying water pipes under the road, is there any regulation or document (snip) that governs the part with which it is allowed to make a puncture? I mean the roadway, curb, ramp and the like. That is, how much to retreat from the asphalt, roadside and other things.

Visitors Comments
  1. Masha

    Hello! In fact, you just need recommendations and regulatory documents that establish the rules for such pipe laying, if you briefly outline the essence of your question. There are a lot of documentation on your request.

    This is, first of all:

    1. SNiP 2.07.01-89.
    2. ODM 218.3.083-2016 Guidelines on the methods of trenchless laying of culverts for roads.
    3. TTK. “Laying engineering networks through the carriageway of roads and railways.”
    4. TTK. “Work on closed (trenchless) laying of pipelines in steel protective covers (cases) under highways by horizontal drilling.”
    5. SP 341.1325800.2017 “Underground utilities. Horizontal directional drilling. ” Please note that this set of rules does not apply to “laying with the HDD method new, reconstructed and overhaul pipelines and branches from them, the design of which is carried out in accordance with SP 36.13330, SP 125.13330”.
    6.P. 12.35. table 15 in SP 42.13330.2011 (photo in the appendix).
    7. SP 249.1325800.2016 “Underground communications. Design and construction in a closed and open way. ”

    But why go the hard way and study a bunch of literature? Before carrying out work, it is imperative to go to the local administration for approval and visit the architecture department, why, because it is in fact the owner of the road. And also, because the development of a puncture project involves geotechnical calculations and surveys. All the rules and regulations on your puncture will tell you there, and if you are categorically against any point, then you will look for specific rules of the law. Here you can still advise you to simply shift the development of the project to the shoulders of the relevant organization, which will conduct all the necessary research upon request.

    Do not forget that you are obliged to notify the road inspectorate about the time and place of the specific work and, of course, coordinate everything with Vodokanal. In general, study the documents or go to the local administration right away.